Plan regional failover without breaking data-location requirements

Plan regional recovery using an explicit data-location matrix for databases, object stores, identity, backups and operators, with failover and failback checks.

Last updated

In short

  • Recovery placement includes backups, identity, keys and logs.
  • Replication lag and fencing determine safe database promotion.
  • Failback needs reconciliation after the recovery site accepts writes.
On this page (6)

Architectures · Part of Hybrid

Treat location as a property of the whole recovery path

A regional recovery plan can move more than application servers. Database replicas, object copies, identity services, backup keys, logs and support access may cross different boundaries. If the organization has approved placement requirements, every dependency needs an allowed recovery location before an outage occurs.

This is a reference planning method, not a statement that Pilae offers particular regions or that a design satisfies a legal requirement. Confirm available infrastructure, actual contractual commitments and organizational approval when scoping hybrid placement. A region label alone is not a compliance determination.

Build a dependency and placement matrix

Dependency Primary placement Recovery placement Evidence needed
Application runtime Record actual location Approved alternative Capacity reservation and deployment definition
Database Primary and replicas Promotion candidate Replication topology and lag observations
Object or file storage Active bucket or volume Replica or restored copy Copy rules, versions and encryption configuration
Identity Directory and broker Surviving authentication path Availability and session behavior
Secrets and keys Key-management boundary Recovery access path Permissions and outage-access procedure
Logs and backups Every retained destination Restore destination Retention, location and operator access
DNS and certificates Control services Available management path Credentials and dependency ownership

Use actual identifiers in the internal version of this matrix. Terms such as “Europe” or “local cloud” are too broad to diagnose a failed recovery dependency. Record whether the permitted boundary concerns physical storage, processing, administrative access or all three.

Choose the recovery pattern

A cold recovery restores from backups into newly provisioned capacity. A warm recovery maintains some ready infrastructure or replicas. An active arrangement serves traffic from more than one location. Each pattern has a different cost, recovery time and consistency burden.

Pattern Capacity commitment Main operational risk
Backup restore Lowest continuously running recovery footprint Provisioning and large-data download take too long
Warm standby Reserved or running secondary resources Replica lag, incomplete dependencies or untested promotion
Active across sites Multiple live serving paths Conflicting writes and complex failure detection

PostgreSQL’s standby documentation explains replication and promotion concepts. A replica’s existence does not establish zero data loss. Record the replication mode, observed lag and behavior when connectivity fails. For object storage, S3 replication documentation illustrates the distinction between same-region and cross-region asynchronous copies. That is a provider-specific example; verify equivalent behavior for the actual storage product selected.

Establish the write-authority rule

The central failover question is which system may accept writes. Before promoting a database replica, fence the old primary through the chosen control mechanism. A network partition can make a healthy primary look unavailable from one location while it continues accepting client writes elsewhere.

Define who authorizes promotion, what evidence they require and how the old writer is prevented from returning independently. DNS changes alone do not necessarily fence an existing connection or an application with a cached address. Include background workers, scheduled jobs and administrative tools in the write-path inventory.

A synthetic invoice-processing workload makes the issue concrete: if both sites process the same queued request, two external invoices may be created even when the databases later reconcile. Coordinate queue state and idempotency alongside database promotion.

Run a dependency-aware exercise

Begin with a tabletop review using the placement matrix. Then perform an isolated or explicitly scheduled drill that removes access to the primary location. Record when the failure is detected, when the promotion decision is made, when the service becomes usable and when data validation finishes.

Check Passing evidence
Authentication Approved users can sign in through the surviving dependency path
Database Expected committed marker is present within the accepted loss boundary
Files Referenced objects open and correspond to database records
Secrets Recovery services can obtain only the credentials they need
Background work Accepted jobs are reconciled without duplicate external effects
Location New data, logs and backups remain inside the approved destinations
User access Old endpoint cannot accept unintended writes

Do not test only the public homepage. Exercise a complete transaction that reads and writes the application’s real dependency chain using synthetic data.

Plan failback before failover

Once the recovery location accepts writes, it contains a new authoritative history. Returning to the original site requires transferring that state or rebuilding the original site as a replica of the new primary. Simply pointing DNS back can discard valid work or create two writers.

Record the replication direction, resynchronization method and validation steps for failback. Recheck object versions, queues and external side effects, not just database row counts. Keep incident snapshots or evidence under the approved retention policy until reconciliation is complete.

Pin database, application and storage-tool versions in the recovery definition. Verify licences and quotas for the second location, including any dormant-service activation requirement. A recovery plan that depends on an unavailable licence server or unapproved support access is incomplete.

Accept the design when the drill demonstrates the required service recovery, data boundary and placement evidence. Publish measured outcomes only for the configuration actually exercised, and review the plan whenever a dependency, region, contract or operating owner changes.

Sources and further reading

Use the linked documentation to confirm the version, edition and contract that apply to your project.

Review our recovery placement

Bring approved locations, dependency owners, recovery objectives and the current database and storage topology.